- ACME Solar's subsidiary ACME Sigma Urja commissioned 51.87 MW of battery energy storage at two projects near Rawatbhata, Chittorgarh, Rajasthan, on 20 November 2026.
- That is 35.81 MW / 148.645 MWh for a project with a Tata Power power purchase agreement, and 16.06 MW / 69.678 MWh for a second, larger project at the same site.
- Commercial operation of both is set for 22 November 2026, and the subsidiary's commissioned battery storage now totals 175.72 MW / 733.939 MWh.
What it means for ACME Solar's business
Storage starts supplying
- With commercial operation set for 22 November 2026, the newly commissioned batteries can start supplying power under their contracts. The Tata Power project has a signed power purchase agreement.
Most of the Tata project's storage is done
- 35.81 MW of the Tata project's 50 MW battery component is commissioned, about 72%. Only the battery part of that project is running so far.
The larger project is still being built
- The second project has 250 MW / 1,069 MWh of storage planned. The filings do not say how much of it is done in total.
What the filing says
Tata Power project
- Commissioned: 35.81 MW / 148.645 MWh of discharge capacity (installed 35.81 MW / 160.48 MWh), out of 50 MW / 209 MWh of discharge capacity (installed 50 MW / 220 MWh).
- This is the battery component of the Tata FDRE power project; only the battery component is commissioned so far.
- Power purchase agreement: signed with The Tata Power Company Limited.
- Commercial operation date: 22 November 2026.
Second project at the same site
- Commissioned on 20 November 2026: a further 16.06 MW / 69.678 MWh of discharge capacity (installed 16.06 MW / 75.225 MWh), out of 250 MW / 1,069 MWh (installed 250 MW / 1,150 MWh).
- This follows an update dated 31 October 2026. Commercial operation date: 22 November 2026.
Total so far
- ACME Sigma Urja's cumulative commissioned battery discharge capacity: 175.72 MW / 733.939 MWh (installed 175.72 MW / 792.418 MWh).
- Location: village Neemri, Rawatbhata tehsil, Chittorgarh district, Rajasthan. ACME Solar filed both updates on 20 November 2026.
Why it matters
What FDRE means
- Firm and dispatchable renewable energy: renewable power paired with storage so it can be supplied at set times, including when the sun is not shining.
MW versus MWh
- MW is how much power the batteries can deliver at once. MWh is how much energy they store, so 148.645 MWh at 35.81 MW is roughly four hours of supply.
What the filing does not say
- It does not give the tariff, the revenue from these batteries, or when the rest of each project will be done.
What to watch next
- Further commissioning updates on both projects, including the rest of the Tata FDRE project beyond its batteries.
Funds that hold ACME Solar
- HSBC Midcap Fund1.6% of the fund
- HDFC Value Fund1.5% of the fund
- Nippon India Small Cap Fund1.3% of the fund
- Tata Small Cap Fund0.99% of the fund
- Canara Robeco Small Cap Fund0.91% of the fund
- Kotak Small Cap Fund0.87% of the fund
- HDFC Multi Cap Fund0.74% of the fund
- PGIM India Midcap Fund0.63% of the fund
- HDFC Flexi Cap Fund0.57% of the fund
- Kotak Large Cap Fund0.53% of the fund
and 4 more
From each fund house's October 2026 portfolio.
Source: Exchange filings
ACME Solar: questions
What did ACME Solar commission?
51.87 MW of battery energy storage at two projects in Chittorgarh, Rajasthan, on 20 November 2026: 35.81 MW for a Tata Power project and 16.06 MW for a second project, according to its filings that day.
What does the battery commissioning mean for ACME Solar's business?
The batteries are set to begin commercial operation on 22 November 2026, so they can start supplying under their contracts. Its subsidiary's commissioned storage now totals 175.72 MW / 733.939 MWh.
Who buys power from ACME Solar's Tata FDRE project?
The Tata Power Company Limited, under a signed power purchase agreement.
How much battery storage has ACME Sigma Urja commissioned in total?
175.72 MW / 733.939 MWh of discharge capacity (installed 175.72 MW / 792.418 MWh), after the 20 November 2026 additions.
This page is educational research based on company filings. It is not a recommendation to buy or sell any security or fund, or personalised investment advice. Investments in securities market are subject to market risks. Read all related documents carefully before investing. Registration granted by SEBI, enlistment with IAASB and certification from NISM in no way guarantee performance of the intermediary or provide any assurance of returns to investors.


