- The second 660 MW unit of SJVN's Buxar thermal power project in Bihar was dedicated to the nation on 21 November 2026. The unit involved an investment of ₹7,221.09 crore.
- With both units commercially operational, the plant has reached its full 1,320 MW. Its total approved revised cost is ₹14,269.40 crore.
- 85% of the plant's power is allocated to Bihar under a long-term power purchase agreement, and its coal comes from Central Coalfields under a fuel supply agreement.
What it means for SJVN's business
A quarter of SJVN's capacity
- SJVN says it has 4,931.50 MW of installed capacity. The 1,320 MW Buxar plant is about 27% of that, and the new unit alone about 13%.
Most of the power has a buyer
- 85% of the output is tied to Bihar under a long-term power purchase agreement, so most of the new unit's power is already contracted.
Coal supply is arranged
- A long-term fuel supply agreement with Central Coalfields, a Coal India subsidiary, covers the plant's domestic coal.
A large project now running
- The ₹14,269.40 crore project is now fully built, and SJVN still has 3,860.50 MW of capacity under construction.
What the filing says
The plant
- Location: Chausa, Buxar district, Bihar. Two units of 660 MW each, 1,320 MW in all.
- Built by SJVN Thermal Private Limited, a wholly owned subsidiary of SJVN.
- Technology: ultra-supercritical, with modern emission-control systems.
Timeline and cost
- Foundation stone laid on 9 March 2019. Unit 1 (660 MW) was inaugurated on 22 August 2025.
- Unit 2 (660 MW) was dedicated on 21 November 2026, involving an investment of ₹7,221.09 crore.
- Total approved revised cost of the project: ₹14,269.40 crore. SJVN filed this on 21 November 2026.
Output and buyers
- Expected generation: about 9,828.72 million units a year at an 85% plant load factor.
- 85% of the power is allocated to Bihar under a long-term power purchase agreement.
- Coal: a fuel supply agreement with Central Coalfields Limited, a Coal India subsidiary.
Why it matters
What commercial operation means
- A unit that is commercially operational supplies power to its buyers under the power purchase agreement, rather than running on test.
What plant load factor is
- Plant load factor is how much power a plant produces compared with running at full capacity all year. The 9,828.72 million units figure assumes 85%.
What the filing does not say
- It does not give the tariff, the date Unit 2 began commercial operation, or what Unit 2 will add to SJVN's revenue.
What to watch next
- How much the plant actually generates, and progress on SJVN's 3,860.50 MW under construction.
Source: Exchange filings
SJVN: questions
What happened at SJVN's Buxar plant?
Its second 660 MW unit was dedicated to the nation on 21 November 2026. With both units commercially operational, the plant is at its full 1,320 MW, according to SJVN's press release filed that day.
What does Buxar Unit 2 mean for SJVN's business?
It completes a 1,320 MW plant that makes up about 27% of SJVN's 4,931.50 MW installed capacity, with 85% of the power allocated to Bihar under a long-term agreement.
How much did SJVN's Buxar project cost?
Its total approved revised cost is ₹14,269.40 crore. Unit 2 alone involved an investment of ₹7,221.09 crore.
Who buys power from the Buxar plant?
85% of its power is allocated to Bihar under a long-term power purchase agreement, SJVN says.
This page is educational research based on company filings. It is not a recommendation to buy or sell any security or fund, or personalised investment advice. Investments in securities market are subject to market risks. Read all related documents carefully before investing. Registration granted by SEBI, enlistment with IAASB and certification from NISM in no way guarantee performance of the intermediary or provide any assurance of returns to investors.