- ACME Solar's subsidiary ACME Alpha Renewables has signed a power purchase agreement (PPA) with NTPC for a 150 MW hybrid project under NTPC's Hybrid-IV tranche.
- The tariff is ₹3.21 per unit for 25 years, and power supply is scheduled to start on 30 June 2028.
- The project combines solar, wind and energy storage across sites in Rajasthan, Gujarat and Madhya Pradesh.
What it means for ACME Solar's business
Contracted revenue from mid-2028
- Once the project runs, ACME Solar sells its power to NTPC at ₹3.21 a unit over a 25-year term.
- Revenue starts only when supply begins, scheduled for 30 June 2028.
Building comes first
- ACME Solar has to build the solar, wind and storage capacity before it earns from it. The filing does not give the project cost or how it will be funded.
More of its pipeline now has a buyer
- The company says 5,080 MW of its 5,380 MW of contracted capacity under construction now has a signed PPA.
- Its total contracted portfolio is 8,370 MW, of which about 3,190 MW is operating, according to the company.
What the filing says
The agreement
- Buyer: NTPC, a domestic customer.
- Contract capacity: 150 MW, under NTPC's Hybrid-IV tranche.
- Tariff: ₹3.21 per unit, already adopted by the Central Electricity Regulatory Commission (CERC).
- Timing: supply is scheduled to start on 30 June 2028 and runs for 25 years from then.
- No promoter interest in NTPC, and not a related-party deal.
The project
- It is connected to the inter-state transmission system, with sites at Bhadla in Rajasthan, Jambkhabalia in Gujarat and Mandsaur in Madhya Pradesh.
- It combines solar and wind with energy storage to supply power through the day, including at peak hours.
- Transmission connectivity is secured for the Jambkhabalia and Mandsaur sites.
Why it matters
What a hybrid project is
- It pairs solar and wind, often with batteries, so supply is steadier than solar alone, which stops at night.
Why CERC adoption matters
- The power regulator has already adopted the tariff, a step that confirms the price before the project is built.
What the filing does not say
- It gives no project cost, funding plan, expected yearly generation or revenue, and no split between solar, wind and storage.
What to watch next
- Construction and financing progress, transmission connectivity for the Bhadla site, and ACME Solar's updates on capacity with signed PPAs.
Source: Exchange filings
ACME Solar: questions
What has ACME Solar signed with NTPC?
A 25-year power purchase agreement for a 150 MW hybrid project under NTPC's Hybrid-IV tranche, at ₹3.21 per unit, according to its 18 November 2026 filing.
What does the NTPC agreement mean for ACME Solar's business?
It gives the project a named buyer and price for 25 years. Revenue begins only when supply starts, scheduled for 30 June 2028, and ACME Solar first has to build the plant.
When will the project start supplying power?
The scheduled start of supply is 30 June 2028.
Where is the project?
Across Bhadla in Rajasthan, Jambkhabalia in Gujarat and Mandsaur in Madhya Pradesh, combining solar, wind and energy storage.
This page is educational research based on company filings. It is not a recommendation to buy or sell any security or fund, or personalised investment advice. Investments in securities market are subject to market risks. Read all related documents carefully before investing. Registration granted by SEBI, enlistment with IAASB and certification from NISM in no way guarantee performance of the intermediary or provide any assurance of returns to investors.